Project Update 01-21-2026

Travel Advisory & Project Update

Starting on Thursday, Jan. 22, 2026 and lasting until about 5 p.m. on Friday, Jan. 30, the City of Littleton and the Colorado Department of Transportation will close the far left turn lane from northbound Santa Fe Drive (US HIghway 85) to westbound Mineral Avenue and close the left lanes in both directions of Mineral Avenue within the project limits. These traffic impacts will remain in place during the nine-day period as part of the Santa Fe and Mineral Improvements project.

The closures are necessary so crews can remove portions of the existing median and begin widening and traffic signal improvements on the west side of the project corridor at the Platte River Parkway and Mineral intersection.

Other work underway sitewide includes backfilling and waterproofing the newly installed concrete box culvert in the southwest portion of the project, installing storm drainage pipe and inlets, potholing, and starting excavation for the new quad roadway.

Traffic Impacts

Thursday, Jan. 22 to Friday, Jan. 30 - Left turn lane closure from north-bound Santa Fe Drive to westbound Mineral Avenue & left lane closures in both directions of Mineral Avenue.

  • The far left turn lane on northbound Santa Fe Drive to westbound Mineral Avenue will be closed from approximately 7 a.m. on Thursday, Jan. 22 to 5 p.m. on Friday, Jan. 30. The second left turn lane will remain open.
  • Left lane closures will also be in place in both directions of Mineral Avenue within the project limits during this nine-day period, reducing traffic to a two-way, single lane alignment.
  • The closures will remain in place 24 hours a day.
  • Please refer to the map for lane closure information.
  • The project limits on Santa Fe Drive extend from Mile Point 201 to MP 202, approximately half a mile south to half a mile north of the Mineral Avenue intersection.
  • The project limits on Mineral Avenue extend from west of Platte River Parkway to east of the Santa Fe Drive intersection.
  • Signs and construction devices will be present to alert the public to the closures and work zone restrictions and to maintain safety.
  • Delays can be expected and caution is advised.
  • Visit LittletonCO.gov/ConeZone for traffic impacts.

Work includes removing asphalt and concrete, and performing traffic signal and utility work at the Platte River Parkway and Mineral Avenue intersection.


Image caption: Location of the lane closures that will be in place from Jan. 22 to Jan. 30 for the City of LIttleton's Santa Fe and Mineral Improvements project.

Categories: 2026, Project Updates
Share Project Update 01-21-2026 on Facebook Share Project Update 01-21-2026 on Twitter Share Project Update 01-21-2026 on Linkedin Email Project Update 01-21-2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>