Santa Fe and Mineral Improvements

Major improvements are underway at South Santa Fe Drive and West Mineral Avenue to reduce congestion and improve safety.
This is one of the busiest intersections in the region, carrying up to 60,000 vehicles a day on Santa Fe and 30,000 on Mineral, with traffic expected to nearly double by 2040.
To address this, the City of Littleton is building a new quadrant roadway in the southwest corner of the intersection.
This design moves left turns out of the main intersection, improving traffic flow, reducing delays, and increasing safety — while through-traffic and right turns remain largely unchanged.
Instead of a massive flyover, the quadrant road provides major safety and traffic improvements at a much lower cost and with far less land impact.
The Santa Fe and Mineral Improvements Project includes:
- New traffic signals;
- Updated lane configurations and improved traffic flow;
- Safer crossings and connections for pedestrians and cyclists;
- Better access and operations for transit users.
These upgrades will help the area function better as River Park, the mixed-use development southwest of the intersection, moves forward.
Construction on the project began in late 2025, and is expected to finish in 2027. The total cost is expected to be $21.4 million, with most funding coming from federal grants and developer contributions, and about $2.8 million from the City of Littleton.
Stay informed
- Traffic impacts will be posted to the Cone Zone page at LittletonCO.gov/ConeZone
- Subscribe to receive email updates from our project partner, Estate Media
- Receive text updates by texting quadroadway to 888-219-9094

Major improvements are underway at South Santa Fe Drive and West Mineral Avenue to reduce congestion and improve safety.
This is one of the busiest intersections in the region, carrying up to 60,000 vehicles a day on Santa Fe and 30,000 on Mineral, with traffic expected to nearly double by 2040.
To address this, the City of Littleton is building a new quadrant roadway in the southwest corner of the intersection.
This design moves left turns out of the main intersection, improving traffic flow, reducing delays, and increasing safety — while through-traffic and right turns remain largely unchanged.
Instead of a massive flyover, the quadrant road provides major safety and traffic improvements at a much lower cost and with far less land impact.
The Santa Fe and Mineral Improvements Project includes:
- New traffic signals;
- Updated lane configurations and improved traffic flow;
- Safer crossings and connections for pedestrians and cyclists;
- Better access and operations for transit users.
These upgrades will help the area function better as River Park, the mixed-use development southwest of the intersection, moves forward.
Construction on the project began in late 2025, and is expected to finish in 2027. The total cost is expected to be $21.4 million, with most funding coming from federal grants and developer contributions, and about $2.8 million from the City of Littleton.
Stay informed
- Traffic impacts will be posted to the Cone Zone page at LittletonCO.gov/ConeZone
- Subscribe to receive email updates from our project partner, Estate Media
- Receive text updates by texting quadroadway to 888-219-9094
-
Travel Advisory
Share Travel Advisory on Facebook Share Travel Advisory on Twitter Share Travel Advisory on Linkedin Email Travel Advisory linkWe appreciate the public’s patience as we enter another important phase of the project. If possible, alternative routes that avoid the project area are highly encouraged during this temporary traffic pattern.
Starting April 27 - Mineral Avenue Traffic Shift
Starting on Monday night, April 27 and lasting until further notice, both directions of traffic on Mineral Avenue from just west of the Santa Fe Drive (US Highway 85) intersection to west of Platte River Parkway will be shifted to the north side of the roadway into a two-way, single-lane alignment.
To accommodate this reduced alignment and keep east-west traffic flowingContinue reading
We appreciate the public’s patience as we enter another important phase of the project. If possible, alternative routes that avoid the project area are highly encouraged during this temporary traffic pattern.
Starting April 27 - Mineral Avenue Traffic Shift
Starting on Monday night, April 27 and lasting until further notice, both directions of traffic on Mineral Avenue from just west of the Santa Fe Drive (US Highway 85) intersection to west of Platte River Parkway will be shifted to the north side of the roadway into a two-way, single-lane alignment.
To accommodate this reduced alignment and keep east-west traffic flowing, the traffic signals at the Platte River Parkway and Mineral Avenue intersection will be removed, with north-south access limited to right turn lanes only to and from westbound Mineral Avenue. Detour routes will be posted to access eastbound Mineral Avenue via Aspen Grove and Santa Fe Drive.
This temporary traffic pattern will remain in place while crews widen the south portion of the roadway and make traffic signal and pedestrian improvements as part of the Santa Fe and Mineral Improvements project.
Location and configuration of the Mineral Avenue traffic shift.Traffic Impacts
The following impacts will be in place during the Mineral Avenue traffic shift:
- Starting on Monday night, April 27, both directions of traffic on Mineral Avenue from west of the Santa Fe Drive intersection to west of South Platte River Parkway, will be shifted north and reduced to a two-way single-lane alignment.
- The shift will be implemented during overnight hours on Monday, April 27 and in place from 7 a.m. on Tuesday, April 28 until further notice.
- The traffic signals at the Platte River Parkway and Mineral Avenue intersection will be removed to maintain east-west traffic flows.
- Southbound Platte River Parkway at Mineral Avenue will be reduced to a single right turn lane onto westbound Mineral Avenue. No left turns will be permitted.
- Access to eastbound Mineral Avenue to and from Platte River Parkway will be via Aspen Grove and Santa Fe Drive, with detours posted.
- Access to northbound Platte River Parkway from westbound Mineral Avenue will remain in place.
- Please refer to the map for the location and configuration of the traffic shift.
- Delays can be expected and alternate routes are strongly advised.
- Please exercise caution and drive slowly while motorists get used to the reduced alignment and restricted turn lanes.
- A speed limit of 45 mph is in place on Mineral Avenue.
- The project limits on Mineral Avenue extend from west of Platte River Parkway to east of the Santa Fe Drive intersection.
- Signs and construction devices will be present to alert the public to the closures and work zone restrictions.
- Follow traffic impacts at LittletonCO.gov/ConeZone.
Stay Connected!
- Webpage: www.LetsTalkLittleton.org/Santa-Fe-Mineral-Improvements
- Hotline: 720-260-7074
- Email: publicinformation@comcast.net
- Sign up for text alerts: Text quadroadway to 8882199094
- Traffic impacts: LittletonCO.gov/ConeZone
- CDOT lane closures: COtrip.org
-
Scheduled Traffic Impacts — April
Share Scheduled Traffic Impacts — April on Facebook Share Scheduled Traffic Impacts — April on Twitter Share Scheduled Traffic Impacts — April on Linkedin Email Scheduled Traffic Impacts — April link
A separate Travel Advisory will be issued announcing the upcoming traffic shift on Mineral Avenue. Notifications will be sent out if there are any changes to the schedule.
Traffic Impacts - Santa Fe Drive (US Highway 85)
Sunday, April 19 to Monday, April 20 - Southbound Santa Fe Drive - single overnight lane closure & 24/7 right shoulder closure.
- Starting at 7 p.m. on Sunday, April 19 and lasting until 6 a.m. on Monday, April 20 a single lane closure will be in place on southbound Santa Fe Drive, with signs and devices present to maintain safety.
- The right shoulderContinue reading
A separate Travel Advisory will be issued announcing the upcoming traffic shift on Mineral Avenue. Notifications will be sent out if there are any changes to the schedule.
Traffic Impacts - Santa Fe Drive (US Highway 85)
Sunday, April 19 to Monday, April 20 - Southbound Santa Fe Drive - single overnight lane closure & 24/7 right shoulder closure.
- Starting at 7 p.m. on Sunday, April 19 and lasting until 6 a.m. on Monday, April 20 a single lane closure will be in place on southbound Santa Fe Drive, with signs and devices present to maintain safety.
- The right shoulder on southbound Santa Fe Drive will be closed 24/7 starting at 7 a.m. on Monday, April 20 until late June.
- The project limits on Santa Fe Drive extend a half-mile north and south of the Santa Fe Drive and Mineral Avenue intersection, from Mile Point 201 to MP 202 in the City of Littleton.
- Delays can be expected and alternate routes are advised.
- A speed limit of 50 mph is in place on Santa Fe Drive.
- Check the Cone Zone Page or COtrip.org for scheduled traffic impacts.
Work includes setting barrier and preparing the shoulder for a 24/7 closure.
Travel Advisory - Mineral Avenue - Traffic Shift
Monday, April 27 until further notice - Mineral Avenue from west of Santa Fe Drive intersection to west of Platte River Parkway - traffic shift north into two-way single-lane alignment.
- Starting on Monday night, April 27, both directions of traffic on Mineral Avenue from west of the Santa Fe Drive intersection to west of South Platte River Parkway, will be shifted north and reduced to a two-way single-lane alignment.
- The shift will be implemented during overnight hours on Monday, April 27 and in place from 7 a.m. on Tuesday, April 28 until further notice.
- The traffic signals at the Platte River Parkway and Mineral Avenue intersection will be removed to maintain east-west traffic flows.
- Southbound Platte River Parkway at Mineral Avenue will be reduced to a single right turn lane onto westbound Mineral Avenue. No left turns will be permitted.
- Access to eastbound Mineral Avenue to and from Platte River Parkway will be via Aspen Grove and Santa Fe Drive, with detours posted.
- Access to northbound Platte River Parkway from westbound Mineral Avenue will remain in place.
- Please refer to the map for the location and configuration of the traffic shift.
- Delays can be expected and alternate routes are strongly advised.
- Please exercise caution and drive slowly while motorists get used to the reduced alignment and restricted turn lanes.
- A speed limit of 45 mph is in place on Mineral Avenue.
- The project limits on Mineral Avenue extend from west of Platte River Parkway to east of the Santa Fe Drive intersection.
- Signs and construction devices will be present to alert the public to the closures and work zone restrictions.
- Follow traffic impacts at LittletonCO.gov/ConeZone.
Work includes widening the south side of Mineral Avenue and making traffic signal and pedestrian accessibility improvements.
Map of the location and configuration of the Mineral Avenue traffic shift.About the Project
- The project began in late November 2025 with anticipated full completion by fall 2027.
- Normal working hours are 7 a.m. to 5 p.m. Monday to Friday.
- Some overnight work will take place from 7 p.m. to 5 a.m.
Work includes building a quadrant roadway and roundabout, widening Santa Fe Drive and Mineral Avenue, adding new lane configurations, installing new traffic signals, and making area mobility and safety improvements.
Stay Connected!
- Webpage: www.LetsTalkLittleton.org/Santa-Fe-Mineral-Improvements
- Hotline: 720-260-7074
- Email: publicinformation@comcast.net
- Sign up for text alerts: Text quadroadway to 8882199094
- Traffic impacts: LittletonCO.gov/ConeZone
- CDOT lane closures: COtrip.org
-
Project Update - 04-06-2026
Share Project Update - 04-06-2026 on Facebook Share Project Update - 04-06-2026 on Twitter Share Project Update - 04-06-2026 on Linkedin Email Project Update - 04-06-2026 link
This update includes upcoming traffic impacts and other status notifications, as well as construction progress and planned work for the next few weeks for the Santa Fe and Mineral Improvements project in Arapahoe County.
Upcoming Traffic Impacts: Starting in mid-April, the right shoulder on southbound Santa Fe Drive (US Highway 85) will be closed 24/7 for access to the work zone.
In addition, starting later this month or in early May, work will begin on Mineral Avenue west of the Santa Fe intersection, with some traffic impacts expected. A notification will be sent out once dates are confirmed.
Cancelled TrafficContinue reading
This update includes upcoming traffic impacts and other status notifications, as well as construction progress and planned work for the next few weeks for the Santa Fe and Mineral Improvements project in Arapahoe County.
Upcoming Traffic Impacts: Starting in mid-April, the right shoulder on southbound Santa Fe Drive (US Highway 85) will be closed 24/7 for access to the work zone.
In addition, starting later this month or in early May, work will begin on Mineral Avenue west of the Santa Fe intersection, with some traffic impacts expected. A notification will be sent out once dates are confirmed.
Cancelled Traffic Shifts on Santa Fe Drive: The previously scheduled traffic shifts and reduced alignments in both directions of Santa Fe Drive have been cancelled. A notification will be sent out with any changes to the schedule.
Since the last update, crews have made significant progress fine grading and forming and pouring curb and gutter for the new quad roadway extension of Platte River Parkway in the southwest quadrant of the project limits. Other work included forming and pouring the toe wall for the concrete box culvert; placing concrete pipe and inlets for the new drainage system; installing electrical conduit; and excavating adjacent areas.
Planned work on the new quad roadway over the next few weeks includes continued forming and pouring concrete curb and gutter; forming sidewalks; installing median covers; and concrete and asphalt paving. Other scheduled activities sitewide include drilling light pole caissons, installing electrical conduit, and placing concrete storm drainage pipe and inlet structures.
-
Project Update - 03-05-2026
Share Project Update - 03-05-2026 on Facebook Share Project Update - 03-05-2026 on Twitter Share Project Update - 03-05-2026 on Linkedin Email Project Update - 03-05-2026 link
This update includes an amended upcoming travel advisory as well as construction progress and planned work for the next few weeks for the Santa Fe and Mineral Improvements project in Arapahoe County.
Amended Upcoming Travel Advisory: The planned traffic shifts and temporary realignment of both directions of traffic on Santa Fe Drive (US Highway 85) for this month have been postponed. The reason for the postponement is to minimize further impacts to the traveling public.
A notification will be sent out in advance of confirmation of the traffic shifts or any scheduled traffic impacts for the project.
Since the lastContinue reading
This update includes an amended upcoming travel advisory as well as construction progress and planned work for the next few weeks for the Santa Fe and Mineral Improvements project in Arapahoe County.
Amended Upcoming Travel Advisory: The planned traffic shifts and temporary realignment of both directions of traffic on Santa Fe Drive (US Highway 85) for this month have been postponed. The reason for the postponement is to minimize further impacts to the traveling public.
A notification will be sent out in advance of confirmation of the traffic shifts or any scheduled traffic impacts for the project.
Since the last update, crews have made significant progress excavating, placing road base and grading the new quad roadway extension of Platte River Parkway in the southwest quadrant of the project limits. Other work included forming and pouring the toe wall for the concrete box culvert and installing concrete pipe and inlets for the new drainage system.
Planned work on the new quad roadway over the next few weeks includes fine grading; forming and pouring concrete curb and gutter; installing median covers; and paving. Other scheduled activities include ongoing installation of storm drainage pipe and inlet structures, and excavating adjacent areas.

North drone view of the new quad roadway extension of Platte River Parkway. Aerial photography by HDR, Inc.

Ground view of the new quad roadway Platte River Parkway extension. Photography by Estate Media.
-
Project Moving Forward, Traffic Impacts Expected
Share Project Moving Forward, Traffic Impacts Expected on Facebook Share Project Moving Forward, Traffic Impacts Expected on Twitter Share Project Moving Forward, Traffic Impacts Expected on Linkedin Email Project Moving Forward, Traffic Impacts Expected link
Progress is being made on the Santa Fe and Mineral Improvements Project as construction continues on the Denver metro area’s first quadrant road interchange.
A concrete box culvert on the south side of Mineral Avenue at Platte River Parkway has been installed, and grading, soil preparation, and storm sewer installation for the quadrant road are ongoing. A major traffic shift on to accommodate ongoing construction will be implemented in late February.
Progress is being made on the Santa Fe and Mineral Improvements Project as construction continues on the Denver metro area’s first quadrant road interchange.
A concrete box culvert on the south side of Mineral Avenue at Platte River Parkway has been installed, and grading, soil preparation, and storm sewer installation for the quadrant road are ongoing. A major traffic shift on to accommodate ongoing construction will be implemented in late February.
-
Project Update 02-19-2026
Share Project Update 02-19-2026 on Facebook Share Project Update 02-19-2026 on Twitter Share Project Update 02-19-2026 on Linkedin Email Project Update 02-19-2026 link
This update includes notice of an upcoming travel advisory as well as construction progress and planned work for the Santa Fe and Mineral Improvements project in Arapahoe County.
Upcoming Travel Advisory: Starting within the next month, both directions of traffic on Santa Fe Drive (US Highway 85) within the project limits will be shifted east into a temporary alignment to accommodate widening and other work on the west side of the work zone. The shift will take place over a two-night period, with lane closures in place and delays expected. Once implemented, two through lanes and a dedicated single leftContinue reading
This update includes notice of an upcoming travel advisory as well as construction progress and planned work for the Santa Fe and Mineral Improvements project in Arapahoe County.
Upcoming Travel Advisory: Starting within the next month, both directions of traffic on Santa Fe Drive (US Highway 85) within the project limits will be shifted east into a temporary alignment to accommodate widening and other work on the west side of the work zone. The shift will take place over a two-night period, with lane closures in place and delays expected. Once implemented, two through lanes and a dedicated single left turn lane will remain in place in both directions of Santa Fe Drive until further notice. A notification will be sent once dates are confirmed.
Since the last update, crews have finished backfilling and waterproofing the concrete box culvert and have begun installing concrete pipe and inlets for the new drainage system. Ongoing work includes excavating for the new quad roadway, and removing asphalt and concrete on Mineral Avenue west of the Santa Fe Drive intersection.
Planned work over the next two weeks includes excavating and placing road base for the new quad roadway, installing drainage pipe and inlets, and building embankment areas. Other work includes preparing for the traffic shift, removing asphalt and concrete, and replacing the traffic signals at Mineral and Platte River Parkway with three-way stop signs. These signs will remain in place until further notice.
Image caption: Recent views of the concrete box culvert and excavation for the new quad roadway.
-
Project Update 01-21-2026
Share Project Update 01-21-2026 on Facebook Share Project Update 01-21-2026 on Twitter Share Project Update 01-21-2026 on Linkedin Email Project Update 01-21-2026 link
Travel Advisory & Project Update
Starting on Thursday, Jan. 22, 2026 and lasting until about 5 p.m. on Friday, Jan. 30, the City of Littleton and the Colorado Department of Transportation will close the far left turn lane from northbound Santa Fe Drive (US HIghway 85) to westbound Mineral Avenue and close the left lanes in both directions of Mineral Avenue within the project limits. These traffic impacts will remain in place during the nine-day period as part of the Santa Fe and Mineral Improvements project.
The closures are necessary so crews can remove portions of the existing median andContinue reading
Travel Advisory & Project Update
Starting on Thursday, Jan. 22, 2026 and lasting until about 5 p.m. on Friday, Jan. 30, the City of Littleton and the Colorado Department of Transportation will close the far left turn lane from northbound Santa Fe Drive (US HIghway 85) to westbound Mineral Avenue and close the left lanes in both directions of Mineral Avenue within the project limits. These traffic impacts will remain in place during the nine-day period as part of the Santa Fe and Mineral Improvements project.
The closures are necessary so crews can remove portions of the existing median and begin widening and traffic signal improvements on the west side of the project corridor at the Platte River Parkway and Mineral intersection.
Other work underway sitewide includes backfilling and waterproofing the newly installed concrete box culvert in the southwest portion of the project, installing storm drainage pipe and inlets, potholing, and starting excavation for the new quad roadway.
Traffic Impacts
Thursday, Jan. 22 to Friday, Jan. 30 - Left turn lane closure from north-bound Santa Fe Drive to westbound Mineral Avenue & left lane closures in both directions of Mineral Avenue.
- The far left turn lane on northbound Santa Fe Drive to westbound Mineral Avenue will be closed from approximately 7 a.m. on Thursday, Jan. 22 to 5 p.m. on Friday, Jan. 30. The second left turn lane will remain open.
- Left lane closures will also be in place in both directions of Mineral Avenue within the project limits during this nine-day period, reducing traffic to a two-way, single lane alignment.
- The closures will remain in place 24 hours a day.
- Please refer to the map for lane closure information.
- The project limits on Santa Fe Drive extend from Mile Point 201 to MP 202, approximately half a mile south to half a mile north of the Mineral Avenue intersection.
- The project limits on Mineral Avenue extend from west of Platte River Parkway to east of the Santa Fe Drive intersection.
- Signs and construction devices will be present to alert the public to the closures and work zone restrictions and to maintain safety.
- Delays can be expected and caution is advised.
- Visit LittletonCO.gov/ConeZone for traffic impacts.
Work includes removing asphalt and concrete, and performing traffic signal and utility work at the Platte River Parkway and Mineral Avenue intersection.
Image caption: Location of the lane closures that will be in place from Jan. 22 to Jan. 30 for the City of LIttleton's Santa Fe and Mineral Improvements project.
-
Project Breaks Ground
Share Project Breaks Ground on Facebook Share Project Breaks Ground on Twitter Share Project Breaks Ground on Linkedin Email Project Breaks Ground link
Littleton leaders and regional partners broke ground on the Santa Fe and Mineral Improvements Project November 19, kicking off the project to build an innovative “quad road” at the congested intersection.
Following years of public outreach, planning, and design, the intersection of South Santa Fe Drive and West Mineral Avenue will see major improvements aimed at reducing traffic delays and improving safety.
With as many as 60,000 vehicles per day on Santa Fe and 30,000 on Mineral, drivers can currently experience delays of up to 20 minutes during peak times. If the intersection were to remain in the current configurationContinue reading
Littleton leaders and regional partners broke ground on the Santa Fe and Mineral Improvements Project November 19, kicking off the project to build an innovative “quad road” at the congested intersection.
Following years of public outreach, planning, and design, the intersection of South Santa Fe Drive and West Mineral Avenue will see major improvements aimed at reducing traffic delays and improving safety.
With as many as 60,000 vehicles per day on Santa Fe and 30,000 on Mineral, drivers can currently experience delays of up to 20 minutes during peak times. If the intersection were to remain in the current configuration, delays would become significantly worse given traffic volumes are projected to grow to 115,000 vehicles per day through the intersection by 2040 due to anticipated future development in the region.
To address these issues, the city is constructing a new “quadrant roadway” in the southwest corner of the intersection. This innovative design will remove left turn movements from the intersection and reroute left-turning traffic onto a separate roadway, freeing up green-light time for through movements and improving overall flow.
-
Project to Begin this Fall
Share Project to Begin this Fall on Facebook Share Project to Begin this Fall on Twitter Share Project to Begin this Fall on Linkedin Email Project to Begin this Fall link
Construction will begin this fall on the Santa Fe and Mineral Improvements Project, a long-planned upgrade to the most congested intersection in Littleton.
The intersection of Santa Fe Drive and Mineral Avenue will soon see major improvements aimed at reducing traffic delays and improving safety. With as many as 60,000 vehicles per day on Santa Fe and 30,000 on Mineral, drivers can currently experience delays of up to 20 minutes during peak times.
To address these issues, the city is constructing a new quadrant roadway in the southwest corner of the intersection. This innovative design will reroute left-turning traffic ontoContinue reading
Construction will begin this fall on the Santa Fe and Mineral Improvements Project, a long-planned upgrade to the most congested intersection in Littleton.
The intersection of Santa Fe Drive and Mineral Avenue will soon see major improvements aimed at reducing traffic delays and improving safety. With as many as 60,000 vehicles per day on Santa Fe and 30,000 on Mineral, drivers can currently experience delays of up to 20 minutes during peak times.
To address these issues, the city is constructing a new quadrant roadway in the southwest corner of the intersection. This innovative design will reroute left-turning traffic onto a separate roadway, freeing up green-light time for through movements and improving overall flow.
The project includes new traffic signals, lane configurations, and timing adjustments, along with other mobility and safety upgrades in the surrounding area.
Construction is expected to begin this fall and will take approximately two years, with completion anticipated in fall 2027. Work is scheduled to start on land southwest of the intersection. Traffic impacts will be posted to the Cone Zone page at LittletonCO.gov/ConeZone.
-
Learn More About Upcoming Improvements at Santa Fe and Mineral
Share Learn More About Upcoming Improvements at Santa Fe and Mineral on Facebook Share Learn More About Upcoming Improvements at Santa Fe and Mineral on Twitter Share Learn More About Upcoming Improvements at Santa Fe and Mineral on Linkedin Email Learn More About Upcoming Improvements at Santa Fe and Mineral link
The City of Littleton is hosting a self-guided online meeting for residents to learn more about transportation improvements in the Santa Fe Drive and Mineral Avenue area, including Littleton's Santa Fe and Mineral Improvements Project, Mineral Mobility Improvements (East and West), and Douglas County's US-85 Improvements Project.
This area of Littleton is undergoing transportation improvements to enhance safety for motorists, pedestrians, and bicyclists, to reduce traffic congestion, and to provide more convenient and comfortable connections. These planned changes will also enhance many local and regional destinations, including RTD's Mineral Light Rail Station and local businesses.
Visit the self-guided online meetingContinue reading
The City of Littleton is hosting a self-guided online meeting for residents to learn more about transportation improvements in the Santa Fe Drive and Mineral Avenue area, including Littleton's Santa Fe and Mineral Improvements Project, Mineral Mobility Improvements (East and West), and Douglas County's US-85 Improvements Project.
This area of Littleton is undergoing transportation improvements to enhance safety for motorists, pedestrians, and bicyclists, to reduce traffic congestion, and to provide more convenient and comfortable connections. These planned changes will also enhance many local and regional destinations, including RTD's Mineral Light Rail Station and local businesses.
Visit the self-guided online meeting to learn more, submit comments or questions, and sign up for each project distribution list to be notified of project updates. The online meeting will be available through Friday, July 28.
Follow Project
Signup Banner
Timeline
-
2023
Santa Fe and Mineral Improvements has finished this stageFinal design complete
-
2025
Santa Fe and Mineral Improvements is currently at this stageConstruction starts
-
2027
this is an upcoming stage for Santa Fe and Mineral ImprovementsNew quadrant roadway and surrounding improvements completed
Project Progress Photo Gallery
Maps
Driving Through a Quadrant Roadway
News Articles
- 2023 (1)
- 2025 (2)
- 2026 (7)
- Project Updates (4)
Project Documents
Project Contacts
-
Transportation Engineer
Phone 303-795-3863 Email PWProjects@LittletonCO.gov -
Contractor's Hotline
CPhone 720-260-7074 Email PublicInformation@Comcast.net


